Petrojet

Sulfate Removable Facilities (new)

Construction, Pre commissioning for Civil & Mechanical Works for Installation of Sulfate Removable Facilities including the following:

  • Earthworks
  • Concrete Works
  • Under ground networks RTR including Manholes / catch basin / Sumps
  • Fabrication and Erection of Steel Structures (Pipe Racks and N.F Building)
  • Concrete works and Finishing of (5) Buildings
  • Pre-fabrication and Erection C.S Piping including Painting and Hydro-test
  • Pre-fabrication and Erection for intake and rejection pipelines (36 ” and 16 “) C.S Piping including Painting and Hydro-test including (Tie-Ins)
  • Equipment Erection ( 6 Vessels , 29 Pumps and 21 Miscellaneous)
  • Pre-commissioning

Nooros-Abu Madi-El Gamil Pipeline

Execution of a Gas Trunk  Pipeline with total length of 126 km from Nooros to El Gamil passing by Abu Madi Plant in order to increase the extraction of butane and gas supply to UGDC Company’s plant for increasing Propane production.

1st Pipeline with Diameter 24” and Length 35 km from Nooros Fields Area to Abu Madi Plant.

2nd Pipeline With Diameter 32” and Length 91 km from Abu Madi Plant to El Gamil Plant.

Scope of work includes:

  • Polyethylene and Concrete Coating for Pipeline Pipes.
  • Permitting/Land compensation.
  • Backfilling of Manzala Lake for about 2.2 Million m3 of soil.
  • 7 new Valve rooms (1 inside Manzala lake)
  • Receiving facilities in Abu Madi and El Gamil plant
  • About 57 HDD Crossings and 50 Open Cut Crossings.

Project Challenges

  • El Manzala Lake Backfilling: 200.000 m3 (35 Km Length).
  • 55 HDD Crossings ( River Nile, El Salam Canal, Fish Farms, Railway, Highways, …etc)

phosphate fertilizer complex package 2

Joint Venture ( Petrojet- Ballestra )

Engineering, Procurement, Construction of phosphate fertilizer complex package 2 at Ain EL-Sokhna.

the complex includes 5 plants for the production of phosphate and compound fertilizers, and pure phosphoric acid with production capacity of 2100 tons/day

Uncategorized

siba central processing facilities (cpf)

Engineering, Procurement, Construction, Pre-commissioning, Testing and Start-up of the central processing facility (CPF) in  Siba contract area facilities to produce 110 mmcfd of processed gas.

A CPF (an EPF in phase 1, expanded to an FPF in phase 2), located inside the Siba license area

Uncategorized

Zohr gas field development

Construction of an onshore Gas complex (phase 1) with a production capacity of 1.4 BCFD.

The offshore field development includes fabrication of control platform & deep water structures in addition to coating of subsea pipelines. Zohr Offshore field is located 180 km off the onshore plant in the Mediterranean sea and at a depth of 1450 m. The field has a total potential of about 30 TCF in place.

West Nile gas development

Development of gas treatment plant at Burullus to treat gas received from the offshore fields Taurus, Giza fayoum, & Raven. Petrojet scope of work is construction, E & I works. in addition to construction of tanks, fabrication of process equipment. Also it includes Polyethylene & concrete coating for subsea pipelines & fabrication of deep water structures.

ERC Refinery

Execution of  Civil, Mechanical works, steel structure, equipment and pipelines installation and Electrical works

Certified: ISO 9001- ISO 14001
OHSAS 18001 - ISO 17025
ASME Stamps - API Q1 - Hull Structures