AllProjects
Crude Distillation Unit (CDU4)

suez

Nasr Petroleum Co. NPC

Crude Distillation Unit (CDU4)

Engineering, Procurement, Construction, E&I works, pre-commissioning and commissioning and start up works of total 4 crude distillation units with 35 equipment of a total weight 900 tons and steel structures of 10000 tons and a refining capacity of 6.5 mmty Products: LPG, Naphtha, Kerosene, Jet Fuel, Gas Oil, Fuel Oil and Bitumen

Amal waste water treatment plant

Amal petroleum company

Amal waste water treatment plant

The treatment process is carried out by treating industrial waste water through biological, chemical, and mechanical approaches with a capacity of 1250 m3/d The smart processors used in this treatment plant are easy to operate. They are designed to achieve maximum efficiency and ensure the highest quality standards and climate tolerance depending on the plant site

Middle Ring Road Development

Sixth of October City Development Authority

Middle Ring Road Development

EPC of civil works for the development of the middle road within the range of the industrial residential interval of 10.5 km. The works also include the construction of 3 bridges in 6th of October City.

Coker Complex

Suez

Suez Oil Processing Co.

Coker Complex

Consortuim (Petrojet & Enppi) in developing & upgrading of Coker complex including Engineering, Procurement and Construction works

de methanizer column

western desert

gasco

de methanizer column

de methanizer column is 60.9 meters long and weighs 470 tons, it's fabricated in order to increase the production capacity of the Complex’s 4th production line from 600 million ft3/day to 1500 million ft3/day

El Nasr waste water treatment plant

suez

El Nasr petroleum

El Nasr waste water treatment plant

engineering, construction, procurement and commissioning of waste water treatment plant for El Nasr company

Wotech Plant

Wotech Company

Wotech Plant

Engineering, Construction, Procurement, commissioning & Pre commissioining of Wotech plant for medium-density fiberboards (MDF) with production capacity of 205 thousand m3 annually, using technologies by Germany's plant engineering firm Siempelkamp, which carries out the project using rice straw

Metro line 4 phase 1 project
Metro line 4 phase 1 project

construction of Cairo Metro line Phase 1 in consortium with Enppi, Arab Contractors, Hassan Allam , and Concord the works include construction of 3 stations

Sokhna Port Quay wall

Ain El Sokhna

Transport Ministry - Suez Canal Authority

Sokhna Port Quay wall

Construction and Diaphragm works of 800 M quay wall with 18 M Depth including commercial and Logistic Terminal and related facilities, includes installation and pouring of: - Fenders - 450 Piles. - Gaskets – Flexible Joints.

Alexandria Port Quay wall  Rehabilitation

Alexandria

Alexandria Petroleum Company

Alexandria Port Quay wall Rehabilitation

EPC for rehabilitation works of quay walls no.1,2,3,4 & 5 with total length of 875 m & with 12 m depth, including civil and electromechanical works.

tunnels & basic infrastructure   (New administrative capital)

Cairo

New Urban Communities Authority

tunnels & basic infrastructure (New administrative capital)

Supply, implementation and Coordination of the site, infrastructure, buildings, gates, service centers, cinemas and restaurant complex for the central park for the new administrative capital, with an area of (94 acres)

Crude oil depots

General Petroleum Corporation

Crude oil depots

Engineering, Construction and Procurement of (29) crude oil storage tanks with a total capacity of 175,000 m3 for each storaage tank and a diameter of 110 m in areas: Ras Badran (12 tanks) Agrood (6 tanks) shoukair (5 tanks) Ras Gharib (6 tanks)

NewNitrogen fertilizer Complex

Ain El Sokhna

El Nasr co. for intermediate chemicals

Nitrogen fertilizer Complex

Consortuim (Petrojet & thyssenkrupp) in construction of 6 plants with total production capacity up to 1.7 million tons/year

NewNORTH MARTYR AHMED HAMDY TUNNEL

suez

The Armed forces of Engineering Authority

NORTH MARTYR AHMED HAMDY TUNNEL

Petrojet completed construction of North Martyr Ahmed Hamdy tunnel The tunnel has two lanes with a length of 4.250 kilometers and a diameter of 11 meters,

ERC REFINERY

Mostorod - Qalyoubia

GS Engineering & Construction

ERC REFINERY

Petrojet scope of work: execution of Civil, Mechanical, E & I works for ERC refinery Upgrading the existing CORC refinery to eliminate 93,000 tons of Egypt’s sulfur emissions. the refinery will convert lowest value fuel oil into middle & light distillates. ERC will have the capacity to produce 4.2 million tons of refined products per year, including 2.3 million tons of Euro V diesel representing more than 50% of Egypt’s current imports & 600,000 tons of jet fuel.

ZOHR GAS FIELD DEVELOPMENT

Port Said

PETROBEL / ENI

ZOHR GAS FIELD DEVELOPMENT

Construction of onshore gas plant on an area of 2.5 million m2 on 2 phases The first Phase includes inlet facilities, EPF, 4 production Trains, 2 SRUs, Utilities and Flair. It has been completed with gas production capacity that reached 2 BCFD. In parallel and during Completion of the first phase, Petrojet have started construction works in second phase that includes additional 3 production Trains, 2 SRUs, Utilities and Flair. phase 2 aims to increase gas production to more than 2.8 BCFD On the other hand, Petrojet carries out the fabrication of offshore structures for Zohr offshore field that is located 200 km off the onshore plant in the Mediterranean sea operations and at a depth of 1,500 meters. The fabrication works includes fabrication of control platform & deep water structures in addition to coating of 707 km Subsea pipelines with polyethylene and concrete. The Field has a total potenial of about 30 TCF in place.

New New Alamein City - 2,300 acres

New Alamein City

New Urban Communities Authority

New Alamein City - 2,300 acres

Engineering, construction and procurement of civil and mechanical works for 2,300 acres in the southern sector of the new city of El Alamein for infrastructure. The project consists of establishing infrastructure networks (a sewage network, rainwater drainage network, a feeding network and an irrigation network).

NewNetwork of cooling pipes for the central cooling station in the New Administrative Capital

New Administrative capital , cairo

Gas Cool

Network of cooling pipes for the central cooling station in the New Administrative Capital

engineering, construction and procurement of the cooling network in the government district and the financial and business districts in the New Administrative Capital.

NewRehabilitation of the container berth of Damietta Port

meditarranean sea

Damietta container handling company

Rehabilitation of the container berth of Damietta Port

Rehabilitation of the container berth of Damietta Port, with a length of 0,05 mt and a width of 50 m divided into 3 phases each of 350 meters length

SUEZ CANAL CORRIDOR DEVELOPMENT PROJECT ISMAILIA TUNNELS

Ismailia – Egypt

Engineering Authority for Armed Forces

SUEZ CANAL CORRIDOR DEVELOPMENT PROJECT ISMAILIA TUNNELS

A major Egyptian national development project started on August 2014, with the aim of maximizing the role of Suez Canal region as an integrated industrial and economic logistic hub, which will contribute in boosting Egypt’s economic growth. Petrojet scope of work includes: Engineering, Procurement and Construction for 2 motorway tunnels (twin tunnels) under Suez Canal north of Ismailia Road tunnels length (TBM) : 5.82 Km – Open Cut: 1.3 Km Internal Diameter: 11.4 m External Diameter: 12.6 m Distance between tunnels : 12.6 m Concrete wall thickness: 60 cm tunnel clear height: 5.5 m lanes number : 2 lanes/each lane width: 3.65 m Tunnel Slope: 3.3% Deepest point of the tunnel 53 m from sea level and 70 m from land level In addition to Execution of (4) Ventilation and Inspection Shafts each of: (internal Dia 23 m – Depth:80 m).

Green River

new administrative capital

Ministry of housing, utilities & urban communitie

Green River

construction and procurement of buildings, gates, community centers, cinemas, food courts, for the central park of 1the New Administrative Capital on an area of 94 feddans at P-03-A area

Network infrastructure of Dar Misr

6th of october

6th of october authority

Network infrastructure of Dar Misr

engineering, construction and procurement of infrastructure network ( water- sanitary sewege- irrigation -roads) systems with a total length of 8.3 km and asphalt works with a total length of 48000 m2

(7) LPG SPHERICAL TANKS

Alexandria, Egypt

Petrogas

(7) LPG SPHERICAL TANKS

Execution of Civil, Mechanical and Electrical works for (7) storage tanks with a capacity of 2400m3.

(4) LPG SPHERICAL TANKS

Sohag, Egypt

Petrogas

(4) LPG SPHERICAL TANKS

Civil, Mechanical and Electrical works for (2) storage tanks with a capacity of 4000 m3 and (2) storage tanks with a capacity of 2400 m3.

SUMED EXPANSION OF SUMED STORAGE CAPACITY – PHASE IIII

Ain Sokhna – Egypt

Arab Petroleum Pipeline Co. (SUMED)

SUMED EXPANSION OF SUMED STORAGE CAPACITY – PHASE IIII

Construction of 6 Cylindrical Tanks with a total capacity of 175,000 m3, associated with Civil, Piping & Electrical works at Ain Sokhna Terminal

SUMED EXPANSION OF SUMED STORAGE CAPACITY – PHASE III

Alexandria

Arab Petroleum Pipeline Co. (SUMED

SUMED EXPANSION OF SUMED STORAGE CAPACITY – PHASE III

Engineering, Procurement (Except Plates) & Construction of (3) Storage Tanks (120,000 m3 / tank) to increase the Storage capacity for SUMED Co. at Sidi Krir.

NATIONAL DEFENSE COUNCIL RESIDENTIAL BUILDINGS

6th October City

National Defense Council

NATIONAL DEFENSE COUNCIL RESIDENTIAL BUILDINGS

Execution of the third phase of residential and administrative project on 150 feddans. It consists of (72) residential buildings.

NEW SUEZ CANAL – DRY EXCAVATION PHASE

Suez – Egypt

Engineering Authority for Armed Forces

NEW SUEZ CANAL – DRY EXCAVATION PHASE

Dry excavation of New Suez Canal at the section 88km to 89km with total volume 11 million m3.

SUEZ CANAL CONTAINER TERMINAL (SCCT) PHASE II

Port Said – Egypt

Suez Canal Container Terminal Co.

SUEZ CANAL CONTAINER TERMINAL (SCCT) PHASE II

Construction of the SCCT onshore works of Phase II on an area of 640,000m2 in addition to expansion works of the facilities and services of Phase I already in operation.

CAIRO – SUEZ ROAD

Cairo – Suez Road

.General Authority for Roads, Bridges & Transp

CAIRO – SUEZ ROAD

EPC for Two-way road ( Two-way road of Three-Lane / side (1 Concrete Lane for Heavy Loads) ) including associated construction works with total Length: 20 km and total width: 23,5 m

BENHA / ALEXANDRIA (5TH SECTION)

Benha

.General Authority for Roads, Bridges & Transp

BENHA / ALEXANDRIA (5TH SECTION)

EPC of 5th section of Benha/Alexandria road (Two-way road of four-lanes/sides) including associated construction works of interchanges, Bridges, and crossings with total length: 19 Km and total width: 42 m

ELMENIA – RAS GHAREB ROAD

Eastern Desert, Egypt

General Authority for Roads, Bridges & Land Transp

ELMENIA – RAS GHAREB ROAD

EPC for Two-way road (Two-way road of Three-Lane / side) including associated construction works with total Length: 55 km and total width: 23,4 m

6TH OF OCTOBER MAIN CORRIDORS (3RD CORRIDOR)

6th Of October

6th Of October City Authority

6TH OF OCTOBER MAIN CORRIDORS (3RD CORRIDOR)

EPC of 3rd corridor at 6th of october city for the section connecting Zewail university with Wahat road, including associated construction works. It's 2 way road (11 M width) and 2 concrete lanes for heavy loads and 2 bridges

JET BEACH RESORT – AIN SOKHNA

Ain Sokhna – Egypt

PETROJET

JET BEACH RESORT – AIN SOKHNA

Building a Touristic Resort on an Area of 75,420 m2 at Ain Sokhna on the Red Sea Coast.The Resort includes the following: Chalets Area, Hotel Area, Services Area, Landscape, Beach Area

PETROLEUM SPORTIVE CITY

New Cairo – Egypt

Egyptian Sportive Services Co. for Petroleum

PETROLEUM SPORTIVE CITY

Execution of PETROSPORT Sportive City at New Cairo on an area of 45 Feddans including: Outdoor court complex (football, volleyball, basketball, handball, and tennis) Swimming pool • Food court • Stadium

GARDENIA RESIDENTIAL BUILDINGS

Cairo – Suez Desert Road

Engineering Authority of Egyptian Armed Forces

GARDENIA RESIDENTIAL BUILDINGS

Execution of the concrete structure and finishes to the number of (20) Residential Buildings composed of Six levels include core, shell and finishes for the project buildings and units.

EL-TOR CITY RESEDINTIAL BUILDINGS

El-Tor -Sinai

Engineering Authority of Egyptian Armed Forces

EL-TOR CITY RESEDINTIAL BUILDINGS

Execution of 30 Residential Buildings composed of (4) levels including core, shell and finishing works.

NewPETROJET NEW ADMIN. BUILDING

New Cairo – Egypt

PETROJET

PETROJET NEW ADMIN. BUILDING

Building PETROJET’s New Corporate Head Quarter at New Cairo (5th Settlement) on an area of 17,000 m2 as follows: Main Building: 3,100 m2 West Wing : 775 m2 South Wing : 775 m2 Parking : 9,000 m2

ECHEM NEW ADMIN. BUILDING

Cairo – Egypt

Petrochemicals Holding Company (ECHEM)

ECHEM NEW ADMIN. BUILDING

Building ECHEM New Admin Building at New Cairo on an area of 3,000 m2 comprising of a basement, ground floor and four typical floors in addition to a 4,200 m2 auditorium and a 2,225 m2 Services Building.

THARWA PETROLEUM COMPANY NEW ADMIN BUILDING

New Cairo

Tharwa Petroleum Company

THARWA PETROLEUM COMPANY NEW ADMIN BUILDING

Building Tharwa New Admin Building at New Cairo on an area of 4,200 m2 consisting of a basement, ground floor and four typical floors.

MIDTAP NEW ADMIN BUILDING

New Cairo – Egypt

Middle East Oil Tankage and Pipelines Co. (MIDTAP)

MIDTAP NEW ADMIN BUILDING

Building MIDTAP New Admin Building at New Cairo on an area of 4,400 m2 consisting of a basement and four typical floors.

DEVELOPMENT OF ADABIYA PORT

Adabiya Port – Egypt

General Authority for the Suez Canal -SCZone

DEVELOPMENT OF ADABIYA PORT

Construction of Dry Cast Plant inside Al Adabiya port in Suez in two phases on the western coast of Suez Gulf, and it is 17 km away from Suez City.

PORT SAID EAST PORT MAIN ROAD PHASE II (PORT SAID – EGYPT)

Port Said

Port Said Port Authority

PORT SAID EAST PORT MAIN ROAD PHASE II (PORT SAID – EGYPT)

Execution of stage II of the Port Said East Port Main Road. The road passes through an area used before for over 20 years as a dumping area for the dredged soil from the Suez Canal, and reached a height of 8m.

PORT SAID HARBOR NAVIGATION TOWER

Port Said – Egypt

Port Said Port Authority

PORT SAID HARBOR NAVIGATION TOWER

Execution of all construction and finishing works for the navigation complex including a 39m high navigation tower, an administration building on an area of 1200 m2 an underground tank, a power station, gates and fences.

BERTH EAST PORTSAID

East Port Said

Armed Forces Engineering Authority

BERTH EAST PORTSAID

One of the Suez Canal Corridor Development projects and the East portsaid harbor expansion. Engineering, procurement and construction of a Berth with a total length of 500 M.

SEPARATION & METERING UNIT
SEPARATION & METERING UNIT

Weight : Up to 52 Ton Dimensions : Up to L: 21m W: 4.2 m H: 8 m

HEAT EXCHANGERS

مصر

HEAT EXCHANGERS

Material : C.S, S.S, Cu / Ni Alloy Weight : Up to 76 Ton No. of Tubes : 5600 Dimensions : Up to D: 2.7 m L: 14 m Thk: 74 mm

PRESSURE VESSELS
PRESSURE VESSELS

Material : C.S, S.S, Cladded, Alloy & Duplex Material Weight : Up to 330 Ton Pressure : Up to 245 Bar Dimensions : Up to D: 6.6 m L: 42 m Thk: 135 mm

HEATER 10-H-01

Suez – Egypt

Suez Oil Processing Co.

HEATER 10-H-01

Weight :625 Ton Material :C.S. Internal Diameter : 3 – 5 m Length :35 m Plate Thickness : 45 mm

DE-METHANIZER COLUMN 10-C-01 MEDITERRANEAN NGL DEVELOPMENT PROJECT

Port Said & Damietta

UGDC

DE-METHANIZER COLUMN 10-C-01 MEDITERRANEAN NGL DEVELOPMENT PROJECT

Weight : 380 Ton Material : SA 240-304 Internal Diameter : 4.5 m Length : 38 m Plate Thickness : 76 mm

DESALINATION PACKAGES

Egypt

General Petroleum Company - GPC Project

DESALINATION PACKAGES

Material : C.S, S.S, and Alloy / Unit Capacity : Up to 5100 m3/day Dimensions : Up to D: 2.7 m L: 14 m Thk: 74 mm

AIR COOLERS

Egypt

Burullus Gas Company

AIR COOLERS

Material : C.S, S.S & Alloy Material Weight : Up to 160 Ton Dimensions: Up to 14 m x 5.5 m x 4.2 m

ABSORBER-DESORBER COLUMNS

Damietta – Egypt

UHDE Gmbh

ABSORBER-DESORBER COLUMNS

Weight : 175 Ton Material : SA 516-70 Length : 60.9 m Plate Thickness : 24 mm

DE-PROPANIZER TOWER C2C3

Alexandria

GASCO

DE-PROPANIZER TOWER C2C3

Weight : 147 Ton Material : SA 516-70 Internal Diameter : 5 – 3.2 m Length : 35.6 m Plate Thickness : 45-30 mm.

Heat Exchangers & Towers (Egypt)

Western Desert, Egypt

Egyptian Natural Gas Co. (GASCO)

Heat Exchangers & Towers (Egypt)

material : C.S, SS Cu/Ni Alloy Wioght: up to 76 ton No. of tubes: 5600 dimensions : up to D: 2.7 m L:14m Thk: 74mm

LT Separator )

Damietta, Egypt

Petrobel

LT Separator )

Weight: 565 Tons Material: C. Steel Width: 4.0 m. Length: 21 m. Height: 7.0 m.

Condensate Storage Drum 76-MD-01(Egypt)

Damietta, Egypt

KJT Consortium

Condensate Storage Drum 76-MD-01(Egypt)

Weight: 190 Tons Material: SA 516-70 Internal Diameter: 6.5 m. Length: 30 m. Plate Thickness: 30 mm.

De-Methanizer Column 10-C-01 (Egypt)

Port Said & Damietta, Egypt

United Gas Derivatives Co.

De-Methanizer Column 10-C-01 (Egypt)

Equipment Details Weight: 380 Tons Material: SA 240-304 Internal Diameter: 4.5 m. Length: 38 m. Plate Thickness: 76 mm.

ZOHR CONTROL PLATFORM

Petrojet Maadia yard

PETROBEL

ZOHR CONTROL PLATFORM

Fabrication, Load out & sea-fastening of weight : 6000 Ton and Water Depth : 90 m

West Delta Gas Plants Development

western desert

Bechtel

West Delta Gas Plants Development

Executing civil, mechanical and electrical works for onshore facilities to connect to five fields in the concession area north of Alexandria and the western Mediterranean with a production capacity of 2.2 billion cubic feet per day. The works include the construction of the Raven gas station with a production capacity of 900 million cubic feet per day and the development of the Burullus gas station to connect to the Giza-Fayum wells to produce 600 million cubic feet, with the aim of increasing gas production to reach 1.6 billion cubic feet of gas and condensate in addition to the Turous Libra field.

NewSonker Terminal Set up

Ain Sokhna

Sonker

Sonker Terminal Set up

EPC of civil, mechanical and electrical works for 3 GAS OIL Storage tanks, 2 capacity of 40,000 m3 + 1 capacity of 20,000 m3 and 3 LPG Tanks of capacity 50,000 m3. The works includes of Steel structures, pipes and pipeline works

New"Kozzika" Storing Yard & Light Repair Workshop for Cairo Metro Line 1 (G2) Project

The National Authority For Tunnels

"Kozzika" Storing Yard & Light Repair Workshop for Cairo Metro Line 1 (G2) Project

Engineering, Procurement and construction for Storing yard and light Repair Workshop: Interface Management Between G1, G2 and G3

PETROSALAM  PLATFORM

suez

petrosalam

PETROSALAM PLATFORM

The project is Consortium between ENPPI And PETROJET Engineering, procurement, fabrication, Pre-commissioning, and Commissioning assistant for Offshore Production Unit with Drilling offshore Jack Up Rig

NAQ PIII ABU-QIR

Alexandria

Abu Qir Petroleum

NAQ PIII ABU-QIR

Fabrication, Load Out and Sea-Fastening of platform with a total Weight of 3210 Ton and Water Depth : 33 M

NAO & HH PLATFORMS

Red Sea

General Petroleum Company - GPC Project

NAO & HH PLATFORMS

,Fabrication, Procurement and pre-commissioning of offshore platform with total weight 2400 Ton andWater Depth : 23.5 M

AL-AMAL PLATFORM

Red Sea

Aquaterra

AL-AMAL PLATFORM

Engineering, procurement, fabrication and Load Out and Sea-Fastening of platform with total Weight 1055 Ton Water Depth : 25 M

AIN SOKHNA /WADI HAGOOL/AL-HAFAYER CRUDE OIL (30”- 42 KM)

Petroleum Pipelines Co. PPC

AIN SOKHNA /WADI HAGOOL/AL-HAFAYER CRUDE OIL (30”- 42 KM)

Pipe coating works, and civil, mechanical, and electrical works for Ain Sokhna/Wadi hagool/ Al-Hafayer (30”- 42 km) crude oil Pipeline from station (6) at Ain Sokhna to Al Hafayer valve room

AL-GAMIL/DAMIETTA (42”-50 KM)

Damietta

GASCO

AL-GAMIL/DAMIETTA (42”-50 KM)

Engineering, Procurement and Construction of 42”-50 km Pipeline including 23 HDD crossings to connect Al-Gamil valve rooms to New Damietta electric station

Atoll field Development

Port Said

Pharaonic Petroleum Co. (PhPC)

Atoll field Development

Development of ATOLL field that aims to increase production capacity to 380 mmscfd of natural gas. Petrojet scope of work includes Civil, Mechanical, E & I works. it also includes EPC for 2 pressure vessels, rehabilitaion for existing low temperature separator, & fabrication of deep water structures with total weight of 840 tons

NewEl Tina-new capital  (42”-165 KM)

New Capital

Egyptian Natural Gas Co. (GASCO)

El Tina-new capital (42”-165 KM)

Construction of 42”-165 km pipeline split into 2 phases; 1st phase is from El-Tina to Abu Sultan with a length of 92 km including 23 HDD crossings. 2nd phase is from Abu Sultan to the Hot Tap of Dahshour P/L at the New Capital with a length of 73 km including 11 HDD crossings.

New  Baltim South West - 5873 ton

Nile Delta- Baltim concession area

PETROBEL

Baltim South West - 5873 ton

Fabrication, Pre-commissioning, Load out, Sea Fastening & assistance for offshore commissioning & Start-up of Baltim platform in the Mediterranean sea to connect 6 wells from Nodoco plant to Abo-Madi/Al Qoraa area with onshore pipeline 26’-18km. It’s expected to increase production capacity to 700 mm2/D

BURULLUS FACILITIES FOR GAS PROCESSING PLANT (TAURUS/LIBRA)

Egypt

Bp

BURULLUS FACILITIES FOR GAS PROCESSING PLANT (TAURUS/LIBRA)

Rehabilitation of Burulus facilities for gas processing plant of Taurus/Libra wells which have the capacity of processing 600 MMCFD

E-METHANEX METHANOL PLANT

Damietta, Egypt

Techint - (Egyptian Methanex Methanol Company)

E-METHANEX METHANOL PLANT

construction of Methanol plant to produce of 1.3 million ton per year in Damietta on the Mediterranean Sea in Egypt.

PROPYLENE & POLYPROPYLENE (PP) COMPLEX

Port Said – Egypt

UHDE - (Egyptian Propylene & Polypropylene Co. (EP

PROPYLENE & POLYPROPYLENE (PP) COMPLEX

Construction of a petrochemical complex at Port Said, North of Egypt, consisting of a Propylene plant and a Polypropylene plant with respective annual production capacities of 350,000 tons as well as all appurtenant utilities and off-sites, including an air fractionation and refrigerating units, and the required storage tanks. Propylene Plant is based on UHDE’s proprietary STAR Process for Propane dehydrogenation, while Polypropylene Plant is based on Basell’s Spheripol Process.

AMMONIA/UREA FERTILIZER COMPLEX

Abu Qir -Alexandria

Alexfert co./UHDE Gmbh

AMMONIA/UREA FERTILIZER COMPLEX

The establishment of a complete Ammonia/Urea complex including off sites facilities and interconnection to Abu-Qir (1 & 2) with an Ammonia production capacity of 1200 ton/day and Urea Production Capacity of 1925 ton/day

DEVELOPMENT OF PHENOL EXTRACTION UNIT

Egypt

Al- Amreya Petroleum Refining Co.(APRC)

DEVELOPMENT OF PHENOL EXTRACTION UNIT

Developing phenol unit extraction to be replaced by N.M.B for saving environment, and increasing production capacity to 283 KT/year

MAXIMIZING OF GAS RECOVERY UNIT AT ASSUIT REFINERY (VRU)

Assuit Oil Refinery Co.(ASORC

ASORC

MAXIMIZING OF GAS RECOVERY UNIT AT ASSUIT REFINERY (VRU)

Maximizing the efficiency of Gas Recovery Unit to increase LPG production to 400 KT/year

MEDITERRANEAN NGL DEVELOPMENT

Port Said / Damietta - Egypt

United Gas Derivatives Company (UGDC) (JV formed o

MEDITERRANEAN NGL DEVELOPMENT

A natural gas liquids extraction facility relying on natural gas produced from North East Mediterranean fields (Al Temsah, Port Fouad, Habi, and Akhen) to extract natural gas derivatives. It is designed to process 1100 MMCFD to produce 300 thousand tons of LPG for the local market, 280 thousand tons of propane for export, and million barrel per year of condensates, and to supply the olefin complex in the future with Ethane/Propane mixture by 400 thousand tons per year.

ASSIL & KARAM GAS DEVELOPMENT

BED 3 Plant – Western Desert

Enppi - (BAPETCO / SHELL)

ASSIL & KARAM GAS DEVELOPMENT

Project aims at increasing the gas production at BED-3 up to 200 MMSCFD by bringing gas from newly discovered wells at Karam (5 Wells) and Assil (2 Wells) . Development includes a new CO2 Removal Plant (CRP) to remove high CO2 content prior to further processing the gas at the existing BED-3 facilities to meet the export CO2 specifications

MIDOR REFINERY

Alex

Technip

MIDOR REFINERY

Development of a modern grassroots refinery to expand the production capacity from 100,000 BPSD to 160,000 BPSD whilst maximizing distillate production. Petrojet scope of work includes Construction, Precommissioning, & Commissioning assistance.

EGYPTIAN LIQUEFIED NATURAL GAS (LNG) PROJECT

Idku

Bechtel - (Egyptian Liquefied Natural Gas Co. (ELN

EGYPTIAN LIQUEFIED NATURAL GAS (LNG) PROJECT

A two – train Liquefied Natural Gas (LNG) plant each with a capacity of approximately 3.6 MT/Y on approximately 165 hectares of land located 3 km from the town of Idku and 40 km East of Alexandria on the Egyptian Mediterranean coast. Technology utilized is the Phillips Optimized Cascade liquefaction technology. The Facility includes 2 Cryogenic Tanks each with a capacity of 140,000 m3, Common Facilities (including Power Generation, Fire Water Systems and Control Building) and Marine Facilities.

SALAM GAS TRAINS (T3 & T4) PROJECT

Western Desert - Egypt

Petrofac - Khalda Petroleum Co.

SALAM GAS TRAINS (T3 & T4) PROJECT

The target of the project is to increase the productivity of El Salam gas station to 410 MMCFD by doubling the processing units to 4 units then transporting the processed gas by el Obayed /el Amerya pipeline

LINEAR ALKYL BENZENE (LAB) PROJECT

Alexandria, Egypt

ELAB

LINEAR ALKYL BENZENE (LAB) PROJECT

Development of a Linear Alkyl Benzene Plant in Alexandria, North of Egypt with a production capacity of 100,000 Tons/Year. Plant consists of Process Unit–Utilities – Storage Facilities – Service Buildings. EPC Contract is performed by Consortium of (PETROJET – ENPPI – GS), where Engineering & Procurement are performed by ENPPI & GS while PETROJET scope is the Construction and Fabrication works.

ETHANE/PROPANE (C2 / C3) MAXIMIZATION

Alexandria – Egypt

Egyptian Natural Gas Company

ETHANE/PROPANE (C2 / C3) MAXIMIZATION

A project aiming at increasing the production of the C2 – C3 by introducing modification in both Amereya LPG recovery plant and the WDGC in addition to the installation of new facilities at both plants. Turbo expander technology is utilized in both plants to maximize C2 and c3 production. The projects scope of work also covers modifications to upgrade the existing process facilities and utilities at both plants.

NEW PETROCHEMICAL COMPLEX

Alexandria - Egypt

JV (TOYO/ ENPPI

NEW PETROCHEMICAL COMPLEX

Construction of a 460,000 ton/year ethylene plant and a 20,000 ton/year butadiene extraction plant as part of Ethydco’s petrochemical complex. The plant is built based on the most advanced ethylene technology of Lummus Technology of the U.S.. Petrojet scope of work: full construction in addition to fabrication of process equipment

NOOROS-ABU MADI-EL GAMIL PIPELINE

From Nooros to Abu MAdi to El Gamil - Egypt

PETROBEL

NOOROS-ABU MADI-EL GAMIL PIPELINE

Execution of a Gas Trunk Pipeline with total length of 126 km from Nooros to El Gamil passing by Abu Madi Plant in order to increase the extraction of butane and gas supply to UGDC Company’s plant for increasing Propane production. 1st Pipeline with Diameter 24” and Length 35 km from Nooros Fields Area to Abu Madi Plant. 2nd Pipeline With Diameter 32” and Length 91 km from Abu Madi Plant to El Gamil Plant. Scope of work includes: Polyethylene and Concrete Coating for Pipeline Pipes. Permitting/Land compensation. Backfilling of Manzala Lake for about 2.2 Million m3 of soil. 7 new Valve rooms (1 inside Manzala lake) Receiving facilities in Abu Madi and El Gamil plant About 57 HDD Crossings and 50 Open Cut Crossings. Project Challenges El Manzala Lake Backfilling: 200.000 m3 (35 Km Length). 55 HDD Crossings ( River Nile, El Salam Canal, Fish Farms, Railway, Highways, …etc)

New PHOSPHATE FERTILIZER COMPLEX - PACKAGE 2

Ain-Sokhna

El Nasr Co. for intermediate chemicals

PHOSPHATE FERTILIZER COMPLEX - PACKAGE 2

Joint Venture ( Petrojet- Ballestra ) EPC of phosphate fertilizer complex package 2. The complex includes 5 plants for the production of phosphate, compound fertilizers, and pure phosphoric acid with production capacity of 1.3 million ton/year

NewASORC Naphtha Complex Utilities & Offsite

Assiut

Enppi

ASORC Naphtha Complex Utilities & Offsite

Petrojet scope of work includes all Civil & Mechanical Works of both the UTILITIES/OFFSITE and ISBL, including procurement, design, fabrication, inspection, construction, installation, erection, testing, pre-commissioning activities and assistance during commissioning and start up

FUTURE CITY RESIDENTIAL BUILDINGS

Haikestep - cairo – Ismailia Desert Road – Egypt

Engineering Authority of Egyptian Armed Forces

FUTURE CITY RESIDENTIAL BUILDINGS

Execution of 10 residential buildings composed of (6) levels including core, shell, and finishing works within the housing project for the members of the Armed Forces in Future City.

SKID MOUNTED PACKAGES

Egypt

SKID MOUNTED PACKAGES

Material : C.S, S.S, Cladded and Duplex Weight : Up to 220 Ton Dimensions : Up to 21m x 6 m x 6.5 m